The City of La Quinta will mark the beginning of work for the La Quinta Village Streets Project with a Groundbreaking Ceremony on Tuesday, July 23, 2019 at 8 a.m. on Calle Tampico Corridor. The $13.5 million project will include the construction of five new roundabouts to make the roadways safer in the La Quinta Village for pedestrian, bicycle, golf cart, and automobile traffic. The public is invited to join in the celebration.
La Quinta Village Roundabout locations and anticipated start/completion dates:
Stage 1: On Calle Tampico between Avenida Bermudas and Washington Street
Roundabout #1: Calle Tampico at Avenida Bermudas
Roundabout #2: Calle Tampico at Desert Club
|
August 2019 - January 2020
|
Stage 2: On Calle Sinaloa/Avenida 52 between Eisenhower Drive and Desert Club Drive
Roundabout #3: Sinaloa/Avenida 52 at Avenida Bermudas
|
January 2020 - May 2020
|
Stage 3: On Eisenhower Drive between Calle Sinaloa and just passed Calle Tampico
Roundabout #4: Calle Tampico at EisenhowerDrive
Roundabout #5: Eisenhower Drive at Avenida Montezuma
|
May 2020 - October 2020
|